Navigation

Industrial electrical case study

Dewhurst ManufacturingFacility Consolidation

Electrical Engineering, Machinery Integration & Commissioning
Moorebank, NSW

When Dewhurst consolidated two manufacturing operations into one new facility, Braintric worked from planning and engineering through electrical construction, machinery integration, testing and commissioning—helping transform the new location into an operational manufacturing facility.

ClientDewhurst
LocationMoorebank, NSW
Project typeManufacturing Facility Consolidation
SectorLift Component Manufacturing
Duration6 Weeks
DeliveryEngineering to Commissioning
35Machines
8Production Lines
5New Distribution Boards
600 m120 mm² Single-Core Cable
1,400 mMachinery Cabling
1,500 mData Cabling
20CCTV Cameras
6 WeeksProject Delivery

Client & project context

Two Manufacturing Operations. One New Facility.

Dewhurst is an international manufacturer and supplier of components for the lift industry, with operations including Australia.

The Australian operation was consolidating two existing factories into a new manufacturing facility in Moorebank, NSW. Relocating equipment was only one part of the challenge: the new facility needed infrastructure for approximately 35 machines across eight production lines, together with distribution equipment, extraction systems, controls, communications and CCTV.

Braintric approached the facility as an integrated industrial electrical system—not a series of isolated machinery connections.

The challenge

Engineering a New Electrical Environment for Existing Production Equipment

Each machine had its own power requirements, operational characteristics and relationship with the wider production process. The new electrical system needed to accommodate large machinery loads while maintaining appropriate distribution, protection and capacity across the facility.

Machinery positioning, production-line layout, switchboard capacity, maximum demand, submains, cable routes, controls, extraction and communications all had to be considered together. Existing PLC interfaces and variable-speed drives also required assessment, reconfiguration or recommissioning.

Dewhurst manufacturing facility production floor in Moorebank NSW
One integrated environmentMachinery layout, distribution and infrastructure planned together.
Industrial switchboard and power distribution work at Dewhurst facility

Engineering & planning

The Project Started Before the First Cable Was Installed

Braintric held technical meetings with the Dewhurst team to understand the manufacturing process, machinery requirements and planned operation of the new facility. Individual machine loads and current requirements were assessed alongside available electrical capacity and maximum demand.

Machinery positions and production-line layouts were considered with switchboard locations, distribution requirements, submains and cable routes. Braintric then presented the proposed electrical solution, scope and quotation before construction proceeded.

  • Client consultation
  • Site & load assessment
  • Maximum demand
  • Electrical design
  • Construction planning

Electrical infrastructure

Building the Electrical Backbone

Five new distribution boards, new submains, machinery power supplies and extensive industrial containment were delivered across the production areas.

Industrial cable tray installation for Dewhurst manufacturing facility in Moorebank
Elevated cable containment coordinated with the factory layout.
Braintric team installing industrial cable containment in Moorebank factory
Infrastructure installed to serve machinery across eight production lines.

Approximately 600 metres of 120 mm² single-core cable formed part of the larger distribution works, together with approximately 1,400 metres of cabling serving machinery and production equipment.

The electrical backbone had to maintain practical routing, accessibility and coordination across approximately 35 machines while fitting the physical production environment.

Machinery integration

35 Machines. Eight Production Lines.

The objective was not simply to energise individual equipment, but to return complete production systems to operational readiness.

CNC machinery electrical integration at Moorebank manufacturing facility
Large press machinery installed at Dewhurst manufacturing facility
Braintric electrician working on industrial machinery at Dewhurst facility
CNC machineryLaser machineryPress machineryWelding equipmentPaint booth systemsExtraction equipment

Braintric provided the electrical supplies and connections required for the equipment and supported machinery-control integration, including PLC-related interfaces, VSD reconfiguration, fault finding and recommissioning where required.

Controls, VSDs & recommissioning

More Than Power Connections

Industrial machinery relocation frequently involves controls configured around the previous operating environment. Braintric supported control-interface assessment, variable-speed drive configuration, fault finding and integration of supporting equipment such as extraction systems.

Managing infrastructure and machinery integration within the same project reduced the separation between building electrical works and production-equipment requirements.

Braintric electrician assessing machine control components at Dewhurst
Controls and recommissioningMachine requirements assessed within the wider facility system.
Industrial control panel infrastructure at Dewhurst manufacturing facility

Data & CCTV infrastructure

Power, Communications & Site Infrastructure

The scope extended beyond machinery power and distribution. Braintric delivered approximately 1,500 metres of data cabling throughout the facility and installed a 20-camera CCTV system.

Coordinating electrical, communications and security infrastructure allowed multiple essential building systems to progress as part of the facility consolidation rather than as isolated installations.

Testing & commissioning

From Installation to Operational Readiness

Braintric progressed through verification, testing, fault finding and commissioning of the new electrical infrastructure, machinery connections, controls and associated equipment, including VSD reconfiguration and recommissioning where required.

With approximately 35 machines and eight production lines, commissioning was coordinated around the broader relocation program and dependencies between equipment. Braintric remained involved from the original engineering discussions through construction and into operational readiness.

Braintric electrician commissioning industrial machinery at Dewhurst facility
Braintric project team during Dewhurst manufacturing facility consolidation in Moorebank NSW
Braintric project team during the Dewhurst manufacturing facility consolidation in Moorebank, NSW.

Project delivery

Engineering and Construction Working Together

The approximately six-week project was delivered by one electrical engineer, one project manager, three electricians and five apprentices.

Braintric’s role across planning, electrical installation and commissioning provided continuity and enabled technical issues identified during construction or recommissioning to be addressed within the wider system context.

1 Electrical Engineer1 Project Manager3 Electricians5 Apprentices

Project scope

One Coordinated Industrial Delivery Scope

From early technical consultation through final operational support.

01

Engineering & Planning

Client consultation · machine loads · maximum demand · available capacity · layouts · distribution planning

02

Power & Distribution

Main infrastructure · switchboards · five distribution boards · submains · machinery supplies · protection

03

Machinery & Controls

CNC · laser · press · welding · paint booth · extraction · PLC interfaces · VSDs · recommissioning

04

Industrial Infrastructure

Cable tray · containment · 600 m main cable · approximately 1,400 m machinery cabling

05

Data & Security

Approximately 1,500 m data cabling · 20-camera CCTV system · network and CCTV infrastructure

06

Commissioning

Electrical and machinery testing · fault finding · control checks · recommissioning · final support

Outcome

One Facility. Integrated Electrical Infrastructure.

The project brought the electrical requirements of two former manufacturing operations together within one new Moorebank facility.

Braintric delivered the distribution, machinery infrastructure, controls support, data and CCTV systems required for the consolidated manufacturing environment. Most importantly, the electrical infrastructure was developed around production requirements from the planning stage—not added after machinery arrived.

Project photo story

From Empty Facility to Operational Environment

A visual sequence of infrastructure, machinery integration and project delivery.

Wide view of Dewhurst manufacturing facility consolidation in Moorebank NSW
Facility overview and production environment.
Braintric industrial distribution board installation at Dewhurst
Distribution infrastructure.
Industrial extraction equipment electrical integration at Dewhurst
Supporting extraction systems.
Electrical work inside industrial machine control cabinet at Dewhurst
Machine-control integration.
CNC machine electrical installation in Moorebank manufacturing facility
CNC production machinery.

Related capabilities

Related Industrial Solutions

The infrastructure delivered in this project also demonstrates capabilities that support future connected-energy projects.

Future smart-energy pathway: This project delivered industrial electrical, machinery, controls, data and CCTV infrastructure. Braintric can also assess energy metering, Energy Management Systems, solar PV, commercial battery storage, demand management, load optimisation and equipment-level energy visibility for suitable facilities; these systems are not claimed as part of the Dewhurst project.

Industrial projects start with the brief

Planning a Factory Relocation or Industrial Electrical Project?

Whether you are relocating machinery, expanding production, upgrading a factory or planning a new manufacturing facility, Braintric can assess the electrical requirements and develop infrastructure around your operation.